Main Street Project

Main St update

Ridgefield CT: September 28, 2023

Ridgefield Announces Completion of Successful Main Street Project

After nearly 16 months of construction, the Main Street Project has been completed. All phases of the project are now finished and fully operational. The street has been re-landscaped in many areas and proudly displays the beauty of our downtown.

From the very beginning of this project, the Town of Ridgefield, its retailers, residents, and those who contributed to the initial planning of the project, have worked effectively together to ensure the project’s success. While the project did experience delays and some inconvenience, the final result has been well received by the overwhelming majority of the parties involved and the residents of Ridgefield. The Connecticut Department of Transportation was also a strong advocate for the proper planning and delivery of all work by the myriad of contractors associated with the project.

Most importantly, the overall objective of the project has been achieved. With the new signalization, we are beginning to witness a smoother flow of traffic and fewer delays at intersections. Dedicated turning lanes are functioning well, helping to prevent a buildup of traffic.

Rudy Marconi, First Selectman, reflected on the years of advocacy and support for the Main Street Project. “On behalf of the Town of Ridgefield, and all those whose efforts helped make this project a success, I wish to thank you for your patience during the various phases of construction. I believe the end result is something that we can all be proud of and appreciate for years to come.”


Ridgefield, CT: May 22, 2023

The Main Street Project continues to wind down with the last of the new signal lights soon to be installed at Governor Street. In addition, the controllers to manage the new traffic and pedestrian crosswalk signals are due to be installed this week, and tested shortly thereafter. Weather permitting, testing will be completed by the end of May/first week of June; with the new signals going live shortly thereafter. This final stage of the work, combined with the new dedicated turning lanes, will allow Main Street traffic to flow even more smoothly and with less congestion and bottlenecks. 

The trees and bushes planted last Fall are doing well. A handful of plantings will need to be replaced this Spring as they did not survive the winter. The CT DOT and the horticulturalist responsible for the landscaping will attend to the replacement of the necessary trees and bushes. 

Also, concrete work at three corners will be undertaken following completion of the signalization and the removal of the old grey signal poles. 

Finally, the work in the CVS parking lot is underway. While not directly related to the Main Street Project, the renewal of the parking lot will certainly complement the work done on Main Street. New asphalt, lighting, and trees will be a part of the parking area renewal. As the renewal of the lot is being done in phases, the disruption will hopefully not seriously inconvenience shoppers. Over the next two months, the parking area will be thoroughly enhanced. 

We thank you for your patience and support as we complete the Main Street Project. 


UPDATE: 
Ridgefield, CT: March 2, 2023

Main Street Project Moves Towards Early Spring Completion 

Many have asked, “When will the Main Street Project conclude?”  The most recent information obtained from the CT DOT and the electrical contractor indicates that all work will be done by mid-April. The delays are a result of supply chain issues for the new signal lights, crosswalk flashing indicators, and flashing beacons at the mid-block crosswalk. All components must be on site to ensure an efficient work schedule and use of resources. Additionally, any new landscaping that is required will also be completed by mid-April, as well as the concrete work required at each corner. Finally, all remaining street and crosswalk lines will be applied during April as the weather becomes warmer.  

“I would like to thank the merchants and residents of Ridgefield for your understanding and patience as we look to complete the final pieces of the Project,” stated First Selectman Rudy Marconi.

 


Main Street Project Fact Sheet

 


FOR IMMEDIATE RELEASE: 5/8/22

Ridgefield’s Facelift Begins Monday, May 9th
Tree Work Starts as Part of Main Street Project

RIDGEFIELD, CT: Ridgefield's Main Street Project has upheld its architectural character as the town has grown in population, however, increased traffic congestion requires the downtown streets to be upgraded and enhanced. As part of the initial work, several trees will be cleared beginning Monday evening, May 9th. It is anticipated that this effort will be completed during the next one to two weeks; and will occur at night to reduce daytime traffic congestion.

First Selectman Rudy Marconi explains, "After critical meetings among the State DOT, Ridgefield’s Tree Warden, and the landscape architect retained by the Town, it was determined that several trees are threatening the safety of Main Street. This project provides a wonderful opportunity to remove dangerous and dying trees and replace them with beautiful native species. The tree work will help beautify the street, comply with the State's requirements, and improve safety."

The tree work is essential to the overall success of the Main Street Project, which is designed to reduce traffic congestion. Following the clearing of the trees, construction will begin at the intersection of Prospect and Main Streets, and the CVS parking lot. This work will also occur during evening hours.

The Town of Ridgefield is collaborating closely with the State DOT and the construction company to ensure that project timelines meet the needs of downtown merchants and residents. In addition, bi-weekly progress meetings are held to review the project status and upcoming construction phases. Regular updates will be communicated to the public throughout the duration of the project.

For more information, please refer to the ‘Main Street Project Fact Sheet’. Be sure to follow the @TownofRidgefieldCT on Facebook and @CTRidgefield on Twitter or visit https://www.ridgefieldct.org/office-first-selectman/pages/main-street-pr... for important updates during the next six months.